Rep. Jay Hoffman

Filed: 10/29/2025

 

 


 

 


 
10400SB0025ham005LRB104 07069 AAS 29445 a

1
AMENDMENT TO SENATE BILL 25

2    AMENDMENT NO. ______. Amend Senate Bill 25, AS AMENDED,
3with reference to page and line numbers of House Amendment No.
44, by replacing line 1 on page 601 through line 10 on page 632
5with the following:
 
6    "(220 ILCS 5/8-104)
7    Sec. 8-104. Natural gas energy efficiency programs.
8    (a) It is the policy of the State that natural gas
9utilities and the Department of Commerce and Economic
10Opportunity are required to use cost-effective energy
11efficiency to reduce direct and indirect costs to consumers.
12It serves the public interest to allow natural gas utilities
13to recover costs for reasonably and prudently incurred
14expenses for cost-effective energy efficiency measures.
15    (b) For purposes of this Section, "energy efficiency"
16means measures that reduce the amount of energy required to
17achieve a given end use. "Energy efficiency" also includes

 

 

10400SB0025ham005- 2 -LRB104 07069 AAS 29445 a

1measures that reduce the total Btus of electricity and natural
2gas needed to meet the end use or uses. "Cost-effective" means
3that the measures satisfy the total resource cost test which,
4for purposes of this Section, means a standard that is met if,
5for an investment in energy efficiency, the benefit-cost ratio
6is greater than one. The benefit-cost ratio is the ratio of the
7net present value of the total benefits of the measures to the
8net present value of the total costs as calculated over the
9lifetime of the measures. The total resource cost test
10compares the sum of avoided natural gas utility costs,
11representing the benefits that accrue to the system and the
12participant in the delivery of those efficiency measures, as
13well as other quantifiable societal benefits, including
14avoided electric utility costs, to the sum of all incremental
15costs of end use measures (including both utility and
16participant contributions), plus costs to administer, deliver,
17and evaluate each demand-side measure, to quantify the net
18savings obtained by substituting demand-side measures for
19supply resources. In calculating avoided costs, reasonable
20estimates shall be included for financial costs likely to be
21imposed by future regulation of emissions of greenhouse gases.
22The low-income programs described in item (4) of subsection
23(f) of this Section shall not be required to meet the total
24resource cost test.
25    (c) Natural gas utilities shall implement cost-effective
26energy efficiency measures to meet at least the following

 

 

10400SB0025ham005- 3 -LRB104 07069 AAS 29445 a

1natural gas savings requirements, which shall be based upon
2the total amount of gas delivered to retail customers, other
3than the customers described in subsection (m) of this
4Section, during calendar year 2009 multiplied by the
5applicable percentage. Natural gas utilities may comply with
6this Section by meeting the annual incremental savings goal in
7the applicable year or by showing that total cumulative annual
8savings within a multi-year planning period associated with
9measures implemented after May 31, 2011 were equal to the sum
10of each annual incremental savings requirement from the first
11day of the multi-year planning period through the last day of
12the multi-year planning period:
13        (1) 0.2% by May 31, 2012;
14        (2) an additional 0.4% by May 31, 2013, increasing
15    total savings to .6%;
16        (3) an additional 0.6% by May 31, 2014, increasing
17    total savings to 1.2%;
18        (4) an additional 0.8% by May 31, 2015, increasing
19    total savings to 2.0%;
20        (5) an additional 1% by May 31, 2016, increasing total
21    savings to 3.0%;
22        (6) an additional 1.2% by May 31, 2017, increasing
23    total savings to 4.2%;
24        (7) an additional 1.4% in the year commencing January
25    1, 2018;
26        (8) an additional 1.5% in the year commencing January

 

 

10400SB0025ham005- 4 -LRB104 07069 AAS 29445 a

1    1, 2019; and
2        (9) an additional 1.5% in each 12-month period
3    thereafter.
4    (d) Notwithstanding the requirements of subsection (c) of
5this Section, a natural gas utility shall limit the amount of
6energy efficiency implemented in any multi-year reporting
7period established by subsection (f) of Section 8-104 of this
8Act, by an amount necessary to limit the estimated average
9increase in the amounts paid by retail customers in connection
10with natural gas service to no more than 2% in the applicable
11multi-year reporting period. The energy savings requirements
12in subsection (c) of this Section may be reduced by the
13Commission for the subject plan, if the utility demonstrates
14by substantial evidence that it is highly unlikely that the
15requirements could be achieved without exceeding the
16applicable spending limits in any multi-year reporting period.
17No later than September 1, 2013, the Commission shall review
18the limitation on the amount of energy efficiency measures
19implemented pursuant to this Section and report to the General
20Assembly, in the report required by subsection (k) of this
21Section, its findings as to whether that limitation unduly
22constrains the procurement of energy efficiency measures.
23    (e) The provisions of this subsection (e) apply to those
24multi-year plans that commence prior to January 1, 2018. The
25utility shall utilize 75% of the available funding associated
26with energy efficiency programs approved by the Commission,

 

 

10400SB0025ham005- 5 -LRB104 07069 AAS 29445 a

1and may outsource various aspects of program development and
2implementation. The remaining 25% of available funding shall
3be used by the Department of Commerce and Economic Opportunity
4to implement energy efficiency measures that achieve no less
5than 20% of the requirements of subsection (c) of this
6Section. Such measures shall be designed in conjunction with
7the utility and approved by the Commission. The Department may
8outsource development and implementation of energy efficiency
9measures. A minimum of 10% of the entire portfolio of
10cost-effective energy efficiency measures shall be procured
11from local government, municipal corporations, school
12districts, public institutions of higher education, and
13community college districts. Five percent of the entire
14portfolio of cost-effective energy efficiency measures may be
15granted to local government and municipal corporations for
16market transformation initiatives. The Department shall
17coordinate the implementation of these measures and shall
18integrate delivery of natural gas efficiency programs with
19electric efficiency programs delivered pursuant to Section
208-103 of this Act, unless the Department can show that
21integration is not feasible.
22    The apportionment of the dollars to cover the costs to
23implement the Department's share of the portfolio of energy
24efficiency measures shall be made to the Department once the
25Department has executed rebate agreements, grants, or
26contracts for energy efficiency measures and provided

 

 

10400SB0025ham005- 6 -LRB104 07069 AAS 29445 a

1supporting documentation for those rebate agreements, grants,
2and contracts to the utility. The Department is authorized to
3adopt any rules necessary and prescribe procedures in order to
4ensure compliance by applicants in carrying out the purposes
5of rebate agreements for energy efficiency measures
6implemented by the Department made under this Section.
7    The details of the measures implemented by the Department
8shall be submitted by the Department to the Commission in
9connection with the utility's filing regarding the energy
10efficiency measures that the utility implements.
11    The portfolio of measures, administered by both the
12utilities and the Department, shall, in combination, be
13designed to achieve the annual energy savings requirements set
14forth in subsection (c) of this Section, as modified by
15subsection (d) of this Section.
16    The utility and the Department shall agree upon a
17reasonable portfolio of measures and determine the measurable
18corresponding percentage of the savings goals associated with
19measures implemented by the Department.
20    No utility shall be assessed a penalty under subsection
21(f) of this Section for failure to make a timely filing if that
22failure is the result of a lack of agreement with the
23Department with respect to the allocation of responsibilities
24or related costs or target assignments. In that case, the
25Department and the utility shall file their respective plans
26with the Commission and the Commission shall determine an

 

 

10400SB0025ham005- 7 -LRB104 07069 AAS 29445 a

1appropriate division of measures and programs that meets the
2requirements of this Section.
3    (e-5) The provisions of this subsection (e-5) shall be
4applicable to those multi-year plans that commence after
5December 31, 2017. Natural gas utilities shall be responsible
6for overseeing the design, development, and filing of their
7efficiency plans with the Commission and may outsource
8development and implementation of energy efficiency measures.
9A minimum of 10% of the entire portfolio of cost-effective
10energy efficiency measures shall be procured from local
11government, municipal corporations, school districts, public
12institutions of higher education, and community college
13districts; unless a utility files a plan or amended plan under
14the provisions of subsection (e-20), in which case the minimum
15spend for measures from such public customers shall be equal
16to at least 30% of non-residential spending. Five percent of
17the entire portfolio of cost-effective energy efficiency
18measures may be granted to local government and municipal
19corporations for market transformation initiatives.
20    Through calendar year 2026, the The utilities shall also
21present a portfolio of energy efficiency measures
22proportionate to the share of total annual utility revenues in
23Illinois from households at or below 150% of the poverty
24level. Such programs shall be targeted to households with
25incomes at or below 80% of area median income.
26    (e-7) Beginning January 1, 2027, the following

 

 

10400SB0025ham005- 8 -LRB104 07069 AAS 29445 a

1requirements shall be in effect for efficiency programs
2targeted to low-income households. For the purposes of this
3Section, "low-income households" means households with incomes
4at or below 80% of the area median income. Utilities shall
5leverage existing State and federal low-income weatherization
6programs and delivery capacity to the extent practicable.
7Utilities shall also prioritize contracting with
8organizations, government agencies, and businesses with a
9track record of delivering weatherization services in
10low-income communities in this State to deliver any low-income
11programs that are not integrated with State and federal
12low-income weatherization programs.    
13    (e-8) Beginning January 1, 2027, the following
14requirements shall be in effect for efficiency programs
15targeted to low-income households, except for single-fuel gas
16utilities with less than 1,000,000 customers:
17        (1) The portion of the entire budget for efficiency
18    programs that is spent on efficiency programs for
19    low-income households shall be no less than the greater
20    of: (A) 25% or (B) five percentage points more than the
21    proportion of total annual gas sales to non-opt-out retail
22    customers that are consumed by low-income households.
23        (2) The portion of spending on efficiency measures
24    that are targeted to low-income households that is
25    delivered through whole building weatherization programs
26    that comprehensively address building envelope efficiency

 

 

10400SB0025ham005- 9 -LRB104 07069 AAS 29445 a

1    upgrade opportunities as well as other efficiency measures
2    shall be at least 80%.
3        (3) Utilities shall invest in health and safety
4    measures that are appropriate and necessary for
5    comprehensively weatherizing the single-family and
6    multi-family buildings of low-income households, with up
7    to 15% of income-qualified program spending made available
8    for such purposes.    
9    (e-10) A utility providing approved energy efficiency
10measures in this State shall be permitted to recover costs of
11those measures through an automatic adjustment clause tariff
12filed with and approved by the Commission. The tariff shall be
13established outside the context of a general rate case and
14shall be applicable to the utility's customers other than the
15customers described in subsection (m) of this Section. Each
16year the Commission shall initiate a review to reconcile any
17amounts collected with the actual costs and to determine the
18required adjustment to the annual tariff factor to match
19annual expenditures.
20    (e-15) For those multi-year plans that commence prior to
21January 1, 2018, each utility shall include, in its recovery
22of costs, the costs estimated for both the utility's and the
23Department's implementation of energy efficiency measures.
24Costs collected by the utility for measures implemented by the
25Department shall be submitted to the Department pursuant to
26Section 605-323 of the Civil Administrative Code of Illinois,

 

 

10400SB0025ham005- 10 -LRB104 07069 AAS 29445 a

1shall be deposited into the Energy Efficiency Portfolio
2Standards Fund, and shall be used by the Department solely for
3the purpose of implementing these measures. A utility shall
4not be required to advance any moneys to the Department but
5only to forward such funds as it has collected. The Department
6shall report to the Commission on an annual basis regarding
7the costs actually incurred by the Department in the
8implementation of the measures. Any changes to the costs of
9energy efficiency measures as a result of plan modifications
10shall be appropriately reflected in amounts recovered by the
11utility and turned over to the Department.
12    (e-20) The provisions of this Section shall be applicable
13to multi-year plans that commence after the effective date of
14this amendatory Act of the 104th General Assembly and are
15submitted by single fuel service utilities on or before the
16effective date of this amendatory Act of the 104th General
17Assembly. A natural gas utility may propose, as part of its
18submission of a multi-year plan, to increase the amount of
19energy efficiency implemented in any multi-year planning
20period above the level that can be achieved under the spending
21cap set forth in subsection (d) of this Section. The first plan
22to increase energy efficiency may be submitted as an amendment
23to the utility's plan for calendar years 2027 through 2029,
24but any amended plans must be filed with the Commission by
25March 1, 2026 or the effective date of this amendatory Act of
26the 104th General Assembly, whichever is later. In addition to

 

 

10400SB0025ham005- 11 -LRB104 07069 AAS 29445 a

1the policy goals established in subsection (f), the Commission
2shall consider, in determining the appropriateness of a
3proposal, whether the multi-year plan at a minimum:    
4        (1) identifies a cost-effective portfolio of measures
5    and specifies the natural gas savings that are reasonably
6    likely to be achieved by the utility;
7        (2) demonstrates that the plan or modified plan, at a
8    minimum, will result in a portfolio of energy efficiency
9    measures that will provide more natural gas savings than
10    would have been achieved in a plan subject to subsection
11    (c);
12        (3) demonstrates that the plan reflects efforts to
13    coordinate delivery of electric utility efficiency
14    programs where such coordination can reduce costs,
15    increase effectiveness of outreach to customers, and
16    increase savings. A gas utility may count electricity
17    savings toward its gas efficiency savings goals subject to
18    the following limitations:
19            (A) only electricity savings produced as a result
20        of the installation of a gas efficiency measure, such
21        as reductions in electricity consumption by gas
22        furnace fans and electric air conditioners that
23        results from the installation of insulation measures
24        that reduce gas used for space heating, may be
25        counted;
26            (B) such electricity savings may only be counted

 

 

10400SB0025ham005- 12 -LRB104 07069 AAS 29445 a

1        when they are generated in service territories not
2        served by electric utilities subject to Section
3        8-103B;
4            (C) no more than 5% of the total savings claimed
5        toward a gas utility's savings goal may be from such
6        electricity savings. For the purposes of this Section,
7        a kilowatt-hour of savings is equal to 0.03412 gas
8        therms;
9        (4) demonstrates whether an increase in funding is
10    necessary to meet the proposed increase in the amount of
11    energy efficiency;
12        (5) prioritizes income-qualified measures and
13    weatherization measures; and
14        (6) demonstrates that the multi-year plan strikes a
15    reasonable balance between the goals of the following:
16            (A) increasing cost-effective efficiency savings
17        and related greenhouse gas emission reductions;
18            (B) reducing overall gas system costs, recognizing
19        that efficiency investments reduce usage and, in turn,
20        the potential need for system investments over the
21        long-term;
22            (C) increasing energy affordability, especially
23        for low-income customers;
24            (D) within the residential sector, prioritizing
25        investment in weatherization and other measures that
26        reduce heating loads over gas equipment measures; and

 

 

10400SB0025ham005- 13 -LRB104 07069 AAS 29445 a

1            (E) providing a diverse cross-section of
2        opportunities for customers of all rate classes to
3        participate in efficiency programs.
4    For single-fuel gas utilities with less than 1,000,000
5customers, the following requirements shall be in effect for
6efficiency programs targeted to low-income households:
7        (1) For gas utilities with greater than 300,000
8    customers, the portion of the entire budget for efficiency
9    programs that is spent on efficiency programs for
10    low-income households shall be no less than the greater of
11    (A) 25% or (B) five percentage points more than the
12    proportion of total annual gas sales to non-opt-out retail
13    customers that are consumed by low-income households. For
14    gas utilities with 300,000 or fewer customers, the portion
15    of the entire budget for efficiency programs that is spent
16    on efficiency programs for low-income households shall be
17    no less than the greater of (A) 15% or (B) five percentage
18    points more than the proportion of total annual gas sales
19    to non-opt-out retail customers that are consumed by
20    low-income households.
21        (2) The portion of spending on efficiency measures
22    targeted to low-income households that shall be delivered
23    through whole building weatherization programs that
24    comprehensively address building envelope efficiency
25    upgrade opportunities as well as other efficiency measures
26    shall be at least 80%.

 

 

10400SB0025ham005- 14 -LRB104 07069 AAS 29445 a

1        (3) Utilities shall invest in health and safety
2    measures appropriate and necessary for comprehensively
3    weatherizing the single-family and multi-family buildings
4    of low-income households, with up to 15% of
5    income-qualified program spending made available for such
6    purposes.
7    As part of its order approving the plan or modified plan,
8the Commission is authorized to:
9        (1) adjust the limitation on the amount of energy
10    efficiency measures implemented pursuant to subsection (d)
11    to the extent necessary to meet the increase in the amount
12    of energy efficiency approved by the Commission pursuant
13    to this subsection (e-20);
14        (2) adjust the public sector spending requirements
15    pursuant to subsection (e-5);    
16        (3) adopt an incentive mechanism for the utility to
17    meet or exceed the goals associated with its proposed
18    multi-year plan if the utility meets or exceeds the
19    following minimum requirements:
20            (A) the utility proposes a plan budget over the
21        applicable multi-year period that is equal to or
22        greater than 5% of the amounts paid by non-opt-out
23        retail customers in connection with natural gas
24        service in the applicable multi-year period;
25            (B) for efficiency program years 2027 through
26        2029, the utility achieves average incremental annual

 

 

10400SB0025ham005- 15 -LRB104 07069 AAS 29445 a

1        savings of at least 0.7% of total average annual gas
2        sales to non-opt-out retail customers over the years
3        2023 through 2025. For multi-year efficiency program
4        plans beginning after 2029, achieving average
5        incremental annual savings of at least 0.8% of total
6        average annual gas sales to non-opt-out retail
7        customers during the 3-year period ending 2 years
8        prior to the first year of the plan. In all multi-year
9        periods, the minimum incremental annual savings
10        requirement shall be reduced by 0.01 percentage points
11        for every 1 percentage point increase in low-income or
12        moderate-income spending above the minimum levels
13        required by subsection (e-5). In no event shall the
14        minimum incremental annual savings requirement be
15        reduced by more than 0.10 percentage points even if
16        low-income or moderate-income spending is increased by
17        more than 10 percentage points above the minimum
18        levels required by subsection (e-5). The Commission
19        may reduce the magnitude of the minimum savings
20        requirements under this subparagraph (B) if the
21        utility can demonstrate that it is not possible to
22        achieve them with a budget equal to 5% of revenues from
23        eligible customers while meeting other minimum
24        requirements. If a utility attempts to demonstrate
25        that it cannot meet the minimum savings requirements
26        in this paragraph with a budget equal to 5% of revenues

 

 

10400SB0025ham005- 16 -LRB104 07069 AAS 29445 a

1        from eligible customers, and the Commission finds that
2        the utility has not made a sufficiently compelling
3        demonstration, the utility may withdraw its plan and
4        file a revised plan;
5            (C) the utility achieves an average savings life
6        of at least 12 years. Average savings lives may be
7        shorter than the average operational lives of measures
8        if the measures do not produce savings in every year in
9        which they operate or if the savings that measures
10        produce decline during their operational lives; and
11            (D) the utility spends at least 67% of all
12        financial incentive dollars on efficiency measures
13        that (1) reduce the space heating loads of buildings
14        through improvements such as to building envelopes,
15        ventilation systems, space heating distribution
16        systems, and space heating system controls; (2) reduce
17        the water heating loads of buildings such as through
18        insulation of hot water pipes, recovery and reuse of
19        heat from waste water and reductions in the amount of
20        hot water required to meet customer needs; or (3)
21        reduce the process heat loads of industrial
22        facilities. Any spending on health and safety measures
23        shall count toward this requirement. No financial
24        incentive spending on furnaces, boilers, water
25        heaters, and other gas-consuming equipment may be
26        counted toward this requirement; and

 

 

10400SB0025ham005- 17 -LRB104 07069 AAS 29445 a

1        (4) for modified plans, require a compliance filing
2    from the utility to adjust budgets and natural gas savings
3    targets, if necessary, to reflect the final level of
4    customers opting out under subsection (m-1).
5    For the purposes of this subsection (e-20):
6    "Average savings life" means (i) the savings that will be
7realized as a result of a utility's efficiency programs over
8the lives of all efficiency measures divided by (ii) the
9savings that will be produced in the first year after such
10measures are installed.    
11    "Moderate-income" means income between 80% of area median
12income and 300% of the federal poverty limit.    
13    (f) No later than October 1, 2010, each gas utility shall
14file an energy efficiency plan with the Commission to meet the
15energy efficiency standards through May 31, 2014. No later
16than October 1, 2013, each gas utility shall file an energy
17efficiency plan with the Commission to meet the energy
18efficiency standards through May 31, 2017. Beginning in 2017
19and every 4 years thereafter, each utility shall file an
20energy efficiency plan with the Commission to meet the energy
21efficiency standards for the next applicable 4-year period
22beginning January 1 of the year following the filing. For
23those multi-year plans commencing on January 1, 2018, each
24utility shall file its proposed energy efficiency plan no
25later than 30 days after the effective date of this amendatory
26Act of the 99th General Assembly or May 1, 2017, whichever is

 

 

10400SB0025ham005- 18 -LRB104 07069 AAS 29445 a

1later. Beginning in 2021 and every 4 years thereafter, each
2utility shall file its energy efficiency plan no later than
3March 1. If a utility does not file such a plan on or before
4the applicable filing deadline for the plan, then it shall
5face a penalty of $100,000 per day until the plan is filed.
6    Each utility's plan shall set forth the utility's
7proposals to meet the utility's portion of the energy
8efficiency standards identified in subsection (c) of this
9Section, as modified by subsection (d) of this Section, taking
10into account the unique circumstances of the utility's service
11territory. For those plans commencing after December 31, 2021,
12the Commission shall seek public comment on the utility's plan
13and shall issue an order approving or disapproving each plan
14within 6 months after its submission. For those plans
15commencing on January 1, 2018, the Commission shall seek
16public comment on the utility's plan and shall issue an order
17approving or disapproving each plan no later than August 31,
182017, or 105 days after the effective date of this amendatory
19Act of the 99th General Assembly, whichever is later. If the
20Commission disapproves a plan, the Commission shall, within 30
21days, describe in detail the reasons for the disapproval and
22describe a path by which the utility may file a revised draft
23of the plan to address the Commission's concerns
24satisfactorily. If the utility does not refile with the
25Commission within 60 days after the disapproval, the utility
26shall be subject to penalties at a rate of $100,000 per day

 

 

10400SB0025ham005- 19 -LRB104 07069 AAS 29445 a

1until the plan is filed. This process shall continue, and
2penalties shall accrue, until the utility has successfully
3filed a portfolio of energy efficiency measures. Penalties
4shall be deposited into the Energy Efficiency Trust Fund and
5the cost of any such penalties may not be recovered from
6ratepayers. In submitting proposed energy efficiency plans and
7funding levels to meet the savings goals adopted by this Act
8the utility shall:
9        (1) Demonstrate that its proposed energy efficiency
10    measures will achieve the requirements that are identified
11    in subsection (c) of this Section, as modified by
12    subsection (d) of this Section.
13        (2) Present specific proposals to implement new
14    building and appliance standards that have been placed
15    into effect.
16        (3) Present estimates of the total amount paid for gas
17    service expressed on a per therm basis associated with the
18    proposed portfolio of measures designed to meet the
19    requirements that are identified in subsection (c) of this
20    Section, as modified by subsection (d) of this Section.
21        (4) For those multi-year plans that commence prior to
22    January 1, 2018, coordinate with the Department to present
23    a portfolio of energy efficiency measures proportionate to
24    the share of total annual utility revenues in Illinois
25    from households at or below 150% of the poverty level.
26    Such programs shall be targeted to households with incomes

 

 

10400SB0025ham005- 20 -LRB104 07069 AAS 29445 a

1    at or below 80% of area median income.
2        (5) Demonstrate that its overall portfolio of energy
3    efficiency measures, not including low-income programs
4    described in item (4) of this subsection (f) and
5    subsection (e-5) of this Section, are cost-effective using
6    the total resource cost test and represent a diverse cross
7    section of opportunities for customers of all rate classes
8    to participate in the programs.
9        (6) Demonstrate that a gas utility affiliated with an
10    electric utility that is required to comply with Section
11    8-103 or 8-103B of this Act has integrated gas and
12    electric efficiency measures into a single program that
13    reduces program or participant costs and appropriately
14    allocates costs to gas and electric ratepayers. For those
15    multi-year plans that commence prior to January 1, 2018,
16    the Department shall integrate all gas and electric
17    programs it delivers in any such utilities' service
18    territories, unless the Department can show that
19    integration is not feasible or appropriate.
20        (7) Include a proposed cost recovery tariff mechanism
21    to fund the proposed energy efficiency measures and to
22    ensure the recovery of the prudently and reasonably
23    incurred costs of Commission-approved programs.
24        (8) Provide for quarterly status reports tracking
25    implementation of and expenditures for the utility's
26    portfolio of measures and, if applicable, the Department's

 

 

10400SB0025ham005- 21 -LRB104 07069 AAS 29445 a

1    portfolio of measures, an annual independent review, and a
2    full independent evaluation of the multi-year results of
3    the performance and the cost-effectiveness of the
4    utility's and, if applicable, Department's portfolios of
5    measures and broader net program impacts and, to the
6    extent practical, for adjustment of the measures on a
7    going forward basis as a result of the evaluations. The
8    resources dedicated to evaluation shall not exceed 3% of
9    portfolio resources in any given multi-year period.
10    (g) No more than 3% of expenditures on energy efficiency
11measures may be allocated for demonstration of breakthrough
12equipment and devices.
13    (h) Illinois natural gas utilities that are affiliated by
14virtue of a common parent company may, at the utilities'
15request, be considered a single natural gas utility for
16purposes of complying with this Section.
17    (i) If, after 3 years, a gas utility fails to meet the
18efficiency standard specified in subsection (c) of this
19Section as modified by subsection (d), then it shall make a
20contribution to the Low-Income Home Energy Assistance Program.
21The total liability for failure to meet the goal shall be
22assessed as follows:
23        (1) a large gas utility shall pay $600,000;
24        (2) a medium gas utility shall pay $400,000; and
25        (3) a small gas utility shall pay $200,000.
26    For purposes of this Section, (i) a "large gas utility" is

 

 

10400SB0025ham005- 22 -LRB104 07069 AAS 29445 a

1a gas utility that on December 31, 2008, served more than
21,500,000 gas customers in Illinois; (ii) a "medium gas
3utility" is a gas utility that on December 31, 2008, served
4fewer than 1,500,000, but more than 500,000 gas customers in
5Illinois; and (iii) a "small gas utility" is a gas utility that
6on December 31, 2008, served fewer than 500,000 and more than
7100,000 gas customers in Illinois. The costs of this
8contribution may not be recovered from ratepayers.
9    If a gas utility fails to meet the efficiency standard
10specified in subsection (c) of this Section, as modified by
11subsection (d) of this Section, in any 2 consecutive
12multi-year planning periods, then the responsibility for
13implementing the utility's energy efficiency measures shall be
14transferred to an independent program administrator selected
15by the Commission. Reasonable and prudent costs incurred by
16the independent program administrator to meet the efficiency
17standard specified in subsection (c) of this Section, as
18modified by subsection (d) of this Section, may be recovered
19from the customers of the affected gas utilities, other than
20customers described in subsection (m) of this Section. The
21utility shall provide the independent program administrator
22with all information and assistance necessary to perform the
23program administrator's duties including but not limited to
24customer, account, and energy usage data, and shall allow the
25program administrator to include inserts in customer bills.
26The utility may recover reasonable costs associated with any

 

 

10400SB0025ham005- 23 -LRB104 07069 AAS 29445 a

1such assistance.
2    (j) No utility shall be deemed to have failed to meet the
3energy efficiency standards to the extent any such failure is
4due to a failure of the Department.
5    (k) Not later than January 1, 2012, the Commission shall
6develop and solicit public comment on a plan to foster
7statewide coordination and consistency between statutorily
8mandated natural gas and electric energy efficiency programs
9to reduce program or participant costs or to improve program
10performance. Not later than September 1, 2013, the Commission
11shall issue a report to the General Assembly containing its
12findings and recommendations.
13    (l) This Section does not apply to a gas utility that on
14January 1, 2009, provided gas service to fewer than 100,000
15customers in Illinois.
16    (m) Subsections (a) through (k) of this Section do not
17apply to customers of a natural gas utility that have a North
18American Industry Classification System code number that is
1922111 or any such code number beginning with the digits 31, 32,
20or 33 and (i) annual usage in the aggregate of 4 million therms
21or more within the service territory of the affected gas
22utility or with aggregate usage of 8 million therms or more in
23this State and complying with the provisions of item (l) of
24this subsection (m); or (ii) using natural gas as feedstock
25and meeting the usage requirements described in item (i) of
26this subsection (m), to the extent such annual feedstock usage

 

 

10400SB0025ham005- 24 -LRB104 07069 AAS 29445 a

1is greater than 60% of the customer's total annual usage of
2natural gas.
3        (1) Customers described in this subsection (m) of this
4    Section shall apply, on a form approved on or before
5    October 1, 2009 by the Department, to the Department to be
6    designated as a self-directing customer ("SDC") or as an
7    exempt customer using natural gas as a feedstock from
8    which other products are made, including, but not limited
9    to, feedstock for a hydrogen plant, on or before the 1st
10    day of February, 2010. Thereafter, application may be made
11    not less than 6 months before the filing date of the gas
12    utility energy efficiency plan described in subsection (f)
13    of this Section; however, a new customer that commences
14    taking service from a natural gas utility after February
15    1, 2010 may apply to become a SDC or exempt customer up to
16    30 days after beginning service. Customers described in
17    this subsection (m) that have not already been approved by
18    the Department may apply to be designated a self-directing
19    customer or exempt customer, on a form approved by the
20    Department, between September 1, 2013 and September 30,
21    2013. Customer applications that are approved by the
22    Department under this amendatory Act of the 98th General
23    Assembly shall be considered to be a self-directing
24    customer or exempt customer, as applicable, for the
25    current 3-year planning period effective December 1, 2013.
26    Such application shall contain the following:

 

 

10400SB0025ham005- 25 -LRB104 07069 AAS 29445 a

1            (A) the customer's certification that, at the time
2        of its application, it qualifies to be a SDC or exempt
3        customer described in this subsection (m) of this
4        Section;
5            (B) in the case of a SDC, the customer's
6        certification that it has established or will
7        establish by the beginning of the utility's multi-year
8        planning period commencing subsequent to the
9        application, and will maintain for accounting
10        purposes, an energy efficiency reserve account and
11        that the customer will accrue funds in said account to
12        be held for the purpose of funding, in whole or in
13        part, energy efficiency measures of the customer's
14        choosing, which may include, but are not limited to,
15        projects involving combined heat and power systems
16        that use the same energy source both for the
17        generation of electrical or mechanical power and the
18        production of steam or another form of useful thermal
19        energy or the use of combustible gas produced from
20        biomass, or both;
21            (C) in the case of a SDC, the customer's
22        certification that annual funding levels for the
23        energy efficiency reserve account will be equal to 2%
24        of the customer's cost of natural gas, composed of the
25        customer's commodity cost and the delivery service
26        charges paid to the gas utility, or $150,000,

 

 

10400SB0025ham005- 26 -LRB104 07069 AAS 29445 a

1        whichever is less;
2            (D) in the case of a SDC, the customer's
3        certification that the required reserve account
4        balance will be capped at 3 years' worth of accruals
5        and that the customer may, at its option, make further
6        deposits to the account to the extent such deposit
7        would increase the reserve account balance above the
8        designated cap level;
9            (E) in the case of a SDC, the customer's
10        certification that by October 1 of each year,
11        beginning no sooner than October 1, 2012, the customer
12        will report to the Department information, for the
13        12-month period ending May 31 of the same year, on all
14        deposits and reductions, if any, to the reserve
15        account during the reporting year, and to the extent
16        deposits to the reserve account in any year are in an
17        amount less than $150,000, the basis for such reduced
18        deposits; reserve account balances by month; a
19        description of energy efficiency measures undertaken
20        by the customer and paid for in whole or in part with
21        funds from the reserve account; an estimate of the
22        energy saved, or to be saved, by the measure; and that
23        the report shall include a verification by an officer
24        or plant manager of the customer or by a registered
25        professional engineer or certified energy efficiency
26        trade professional that the funds withdrawn from the

 

 

10400SB0025ham005- 27 -LRB104 07069 AAS 29445 a

1        reserve account were used for the energy efficiency
2        measures;
3            (F) in the case of an exempt customer, the
4        customer's certification of the level of gas usage as
5        feedstock in the customer's operation in a typical
6        year and that it will provide information establishing
7        this level, upon request of the Department;
8            (G) in the case of either an exempt customer or a
9        SDC, the customer's certification that it has provided
10        the gas utility or utilities serving the customer with
11        a copy of the application as filed with the
12        Department;
13            (H) in the case of either an exempt customer or a
14        SDC, certification of the natural gas utility or
15        utilities serving the customer in Illinois including
16        the natural gas utility accounts that are the subject
17        of the application; and
18            (I) in the case of either an exempt customer or a
19        SDC, a verification signed by a plant manager or an
20        authorized corporate officer attesting to the
21        truthfulness and accuracy of the information contained
22        in the application.
23        (2) The Department shall review the application to
24    determine that it contains the information described in
25    provisions (A) through (I) of item (1) of this subsection
26    (m), as applicable. The review shall be completed within

 

 

10400SB0025ham005- 28 -LRB104 07069 AAS 29445 a

1    30 days after the date the application is filed with the
2    Department. Absent a determination by the Department
3    within the 30-day period, the applicant shall be
4    considered to be a SDC or exempt customer, as applicable,
5    for all subsequent multi-year planning periods, as of the
6    date of filing the application described in this
7    subsection (m). If the Department determines that the
8    application does not contain the applicable information
9    described in provisions (A) through (I) of item (1) of
10    this subsection (m), it shall notify the customer, in
11    writing, of its determination that the application does
12    not contain the required information and identify the
13    information that is missing, and the customer shall
14    provide the missing information within 15 working days
15    after the date of receipt of the Department's
16    notification.
17        (3) The Department shall have the right to audit the
18    information provided in the customer's application and
19    annual reports to ensure continued compliance with the
20    requirements of this subsection. Based on the audit, if
21    the Department determines the customer is no longer in
22    compliance with the requirements of items (A) through (I)
23    of item (1) of this subsection (m), as applicable, the
24    Department shall notify the customer in writing of the
25    noncompliance. The customer shall have 30 days to
26    establish its compliance, and failing to do so, may have

 

 

10400SB0025ham005- 29 -LRB104 07069 AAS 29445 a

1    its status as a SDC or exempt customer revoked by the
2    Department. The Department shall treat all information
3    provided by any customer seeking SDC status or exemption
4    from the provisions of this Section as strictly
5    confidential.
6        (4) Upon request, or on its own motion, the Commission
7    may open an investigation, no more than once every 3 years
8    and not before October 1, 2014, to evaluate the
9    effectiveness of the self-directing program described in
10    this subsection (m).
11    Customers described in this subsection (m) that applied to
12the Department on January 3, 2013, were approved by the
13Department on February 13, 2013 to be a self-directing
14customer or exempt customer, and receive natural gas from a
15utility that provides gas service to at least 500,000 retail
16customers in Illinois and electric service to at least
171,000,000 retail customers in Illinois shall be considered to
18be a self-directing customer or exempt customer, as
19applicable, for the current 3-year planning period effective
20December 1, 2013.
21    (m-1) For utilities that file an amended plan for the
22period covering calendar years 2027 through 2029, and for all
23utilities for all calendar years covered by a multi-year plan
24commencing on or after January 1, 2030, subsections (a)
25through (k) of this Section do not apply to eligible customers
26of a natural gas utility that have chosen to opt out of

 

 

10400SB0025ham005- 30 -LRB104 07069 AAS 29445 a

1multi-year plans.
2        (1) For purposes of this subsection (m-1), "eligible
3    customer" means any retail customer of a natural gas
4    utility, except for federal, State, municipal and other
5    public customers, with a North American Industry
6    Classification System code number that is 22111 or any
7    such code number beginning with the digits 31, 32, or 33
8    and (i) annual usage in the aggregate of 4,000,000 therms
9    or more within the service territory of the affected gas
10    utility or with aggregate usage of 8,000,000 therms or
11    more in this State; or (ii) using natural gas as feedstock
12    and meeting the usage requirements described in item (i)
13    of this paragraph (1), to the extent such annual feedstock
14    usage is greater than 60% of the customer's total annual
15    usage of natural gas. A determination of whether this
16    subsection is applicable to a customer shall be made for
17    each multi-year plan beginning after January 1, 2026. The
18    criteria for determining whether this subsection is
19    applicable shall be the 12 consecutive billing periods
20    prior to the start of the first year of each such
21    multi-year plan.
22        (2) Within 45 days after the effective date of this
23    amendatory Act of the 104th General Assembly, the
24    Commission shall prescribe the form for notice required
25    for opting out of energy efficiency programs. Within 120
26    days after the Commission's initial issuance of the form

 

 

10400SB0025ham005- 31 -LRB104 07069 AAS 29445 a

1    for notice, customers described in paragraph (1) of this
2    subsection (m-1) may submit completed forms to the natural
3    gas utility. Thereafter, forms must be submitted to the
4    natural gas utility not less than 6 months before the
5    filing date of the gas utility energy efficiency plan
6    described in subsection (f) of this Section; however, a
7    new customer that commences taking service from a natural
8    gas utility after January 1, 2026 may submit a form up to
9    30 days after beginning service. The form for notice for
10    opting out of natural gas energy efficiency programs shall
11    contain the following:
12            (A) a statement indicating that the customer has
13        elected to opt-out;
14            (B) the account numbers for the customer accounts
15        to which the opt out shall apply;
16            (C) the mailing address associated with each
17        customer account identified under subparagraph (B);
18            (D) the customer's certification that, at the time
19        its form was submitted, it qualifies as an eligible
20        customer, as described in paragraph (1) of this
21        subsection (m-1);
22            (E) an American Society of Heating, Refrigerating,
23        and Air Conditioning Engineers (ASHRAE) level 2 or
24        higher audit report conducted by an independent
25        third-party expert identifying cost-effective energy
26        efficiency project opportunities that could be

 

 

10400SB0025ham005- 32 -LRB104 07069 AAS 29445 a

1        invested in over the next 10 years. A customer with a
2        specialized process may use a self-audit process in
3        lieu of an ASHRAE audit;
4            (F) a description of the customer's plans to
5        reallocate funds toward internal energy efficiency
6        efforts identified in the subparagraph (E) report,
7        including, but not limited to: (i) strategic energy
8        management or other programs, including descriptions
9        of targeted buildings, equipment and operations; (ii)
10        eligible energy efficiency measures; and (iii)
11        expected energy savings, itemized by technology. If
12        the subparagraph (E) audit report identifies that the
13        customer currently utilizes the best available energy
14        efficient technology, equipment, programs, and
15        operations, the customer may provide a statement that
16        more efficient technology, equipment, programs, and
17        operations are not reasonably available as a means of
18        satisfying this subparagraph (F); and
19            (G) a verification signed by a plant manager or an
20        authorized corporate officer attesting to the
21        truthfulness and accuracy of the information contained
22        in the application.
23        (3) Upon receipt of a properly and timely noticed
24    request for opt out submitted by an eligible large private
25    energy customer, the natural gas utility shall grant the
26    request and file the request with the Commission, and,

 

 

10400SB0025ham005- 33 -LRB104 07069 AAS 29445 a

1    beginning January 1 of the first year of the next
2    multi-year energy efficiency plan cycle, the opted out
3    customer shall no longer be assessed the costs of the plan
4    and shall be prohibited from participating in that
5    multi-year plan cycle to give the natural gas utility the
6    certainty to design program plan proposals.
7        (4) The request to opt out is only valid for the
8    requested plan cycle. An eligible large private energy
9    customer must also request to opt out for future energy
10    efficiency plan cycles, otherwise the customer will be
11    included in the future energy efficiency plan cycle.    
12    (n) The applicability of this Section to customers
13described in subsection (m) of this Section is conditioned on
14the existence of the SDC program. In no event will any
15provision of this Section apply to such customers after
16January 1, 2020.
17    (o) Utilities' 3-year energy efficiency plans approved by
18the Commission on or before the effective date of this
19amendatory Act of the 99th General Assembly for the period
20June 1, 2014 through May 31, 2017 shall continue to be in force
21and effect through December 31, 2017 so that the energy
22efficiency programs set forth in those plans continue to be
23offered during the period June 1, 2017 through December 31,
242017. Each utility is authorized to increase, on a pro rata
25basis, the energy savings goals and budgets approved in its
26plan to reflect the additional 7 months of the plan's

 

 

10400SB0025ham005- 34 -LRB104 07069 AAS 29445 a

1operation.
2(Source: P.A. 103-613, eff. 7-1-24.)"; and
 
3on page 721, by replacing lines 1 through 4 with the following:
4        "(1) has a nameplate generating capacity no greater
5    than 5,000 kilowatts and is primarily used to offset a
6    customer's electricity load, or as otherwise as defined
7    for community renewable generation projects in Section
8    1-10 of the Illinois Power Agency Act;"; and
 
9on page 810, line 20, after "attributes", by inserting "to
10ensure customers are not double-billed for the same service";
11and
 
12on page 846, by replacing lines 15 through 19 with the
13following:
14    "made pursuant to subsection (b-10) of Section 16-111.5.".