|
| | 10400SB0025ham005 | - 2 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | measures that reduce the total Btus of electricity and natural |
| 2 | | gas needed to meet the end use or uses. "Cost-effective" means |
| 3 | | that the measures satisfy the total resource cost test which, |
| 4 | | for purposes of this Section, means a standard that is met if, |
| 5 | | for an investment in energy efficiency, the benefit-cost ratio |
| 6 | | is greater than one. The benefit-cost ratio is the ratio of the |
| 7 | | net present value of the total benefits of the measures to the |
| 8 | | net present value of the total costs as calculated over the |
| 9 | | lifetime of the measures. The total resource cost test |
| 10 | | compares the sum of avoided natural gas utility costs, |
| 11 | | representing the benefits that accrue to the system and the |
| 12 | | participant in the delivery of those efficiency measures, as |
| 13 | | well as other quantifiable societal benefits, including |
| 14 | | avoided electric utility costs, to the sum of all incremental |
| 15 | | costs of end use measures (including both utility and |
| 16 | | participant contributions), plus costs to administer, deliver, |
| 17 | | and evaluate each demand-side measure, to quantify the net |
| 18 | | savings obtained by substituting demand-side measures for |
| 19 | | supply resources. In calculating avoided costs, reasonable |
| 20 | | estimates shall be included for financial costs likely to be |
| 21 | | imposed by future regulation of emissions of greenhouse gases. |
| 22 | | The low-income programs described in item (4) of subsection |
| 23 | | (f) of this Section shall not be required to meet the total |
| 24 | | resource cost test. |
| 25 | | (c) Natural gas utilities shall implement cost-effective |
| 26 | | energy efficiency measures to meet at least the following |
|
| | 10400SB0025ham005 | - 3 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | natural gas savings requirements, which shall be based upon |
| 2 | | the total amount of gas delivered to retail customers, other |
| 3 | | than the customers described in subsection (m) of this |
| 4 | | Section, during calendar year 2009 multiplied by the |
| 5 | | applicable percentage. Natural gas utilities may comply with |
| 6 | | this Section by meeting the annual incremental savings goal in |
| 7 | | the applicable year or by showing that total cumulative annual |
| 8 | | savings within a multi-year planning period associated with |
| 9 | | measures implemented after May 31, 2011 were equal to the sum |
| 10 | | of each annual incremental savings requirement from the first |
| 11 | | day of the multi-year planning period through the last day of |
| 12 | | the multi-year planning period: |
| 13 | | (1) 0.2% by May 31, 2012; |
| 14 | | (2) an additional 0.4% by May 31, 2013, increasing |
| 15 | | total savings to .6%; |
| 16 | | (3) an additional 0.6% by May 31, 2014, increasing |
| 17 | | total savings to 1.2%; |
| 18 | | (4) an additional 0.8% by May 31, 2015, increasing |
| 19 | | total savings to 2.0%; |
| 20 | | (5) an additional 1% by May 31, 2016, increasing total |
| 21 | | savings to 3.0%; |
| 22 | | (6) an additional 1.2% by May 31, 2017, increasing |
| 23 | | total savings to 4.2%; |
| 24 | | (7) an additional 1.4% in the year commencing January |
| 25 | | 1, 2018; |
| 26 | | (8) an additional 1.5% in the year commencing January |
|
| | 10400SB0025ham005 | - 4 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | 1, 2019; and |
| 2 | | (9) an additional 1.5% in each 12-month period |
| 3 | | thereafter. |
| 4 | | (d) Notwithstanding the requirements of subsection (c) of |
| 5 | | this Section, a natural gas utility shall limit the amount of |
| 6 | | energy efficiency implemented in any multi-year reporting |
| 7 | | period established by subsection (f) of Section 8-104 of this |
| 8 | | Act, by an amount necessary to limit the estimated average |
| 9 | | increase in the amounts paid by retail customers in connection |
| 10 | | with natural gas service to no more than 2% in the applicable |
| 11 | | multi-year reporting period. The energy savings requirements |
| 12 | | in subsection (c) of this Section may be reduced by the |
| 13 | | Commission for the subject plan, if the utility demonstrates |
| 14 | | by substantial evidence that it is highly unlikely that the |
| 15 | | requirements could be achieved without exceeding the |
| 16 | | applicable spending limits in any multi-year reporting period. |
| 17 | | No later than September 1, 2013, the Commission shall review |
| 18 | | the limitation on the amount of energy efficiency measures |
| 19 | | implemented pursuant to this Section and report to the General |
| 20 | | Assembly, in the report required by subsection (k) of this |
| 21 | | Section, its findings as to whether that limitation unduly |
| 22 | | constrains the procurement of energy efficiency measures. |
| 23 | | (e) The provisions of this subsection (e) apply to those |
| 24 | | multi-year plans that commence prior to January 1, 2018. The |
| 25 | | utility shall utilize 75% of the available funding associated |
| 26 | | with energy efficiency programs approved by the Commission, |
|
| | 10400SB0025ham005 | - 5 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | and may outsource various aspects of program development and |
| 2 | | implementation. The remaining 25% of available funding shall |
| 3 | | be used by the Department of Commerce and Economic Opportunity |
| 4 | | to implement energy efficiency measures that achieve no less |
| 5 | | than 20% of the requirements of subsection (c) of this |
| 6 | | Section. Such measures shall be designed in conjunction with |
| 7 | | the utility and approved by the Commission. The Department may |
| 8 | | outsource development and implementation of energy efficiency |
| 9 | | measures. A minimum of 10% of the entire portfolio of |
| 10 | | cost-effective energy efficiency measures shall be procured |
| 11 | | from local government, municipal corporations, school |
| 12 | | districts, public institutions of higher education, and |
| 13 | | community college districts. Five percent of the entire |
| 14 | | portfolio of cost-effective energy efficiency measures may be |
| 15 | | granted to local government and municipal corporations for |
| 16 | | market transformation initiatives. The Department shall |
| 17 | | coordinate the implementation of these measures and shall |
| 18 | | integrate delivery of natural gas efficiency programs with |
| 19 | | electric efficiency programs delivered pursuant to Section |
| 20 | | 8-103 of this Act, unless the Department can show that |
| 21 | | integration is not feasible. |
| 22 | | The apportionment of the dollars to cover the costs to |
| 23 | | implement the Department's share of the portfolio of energy |
| 24 | | efficiency measures shall be made to the Department once the |
| 25 | | Department has executed rebate agreements, grants, or |
| 26 | | contracts for energy efficiency measures and provided |
|
| | 10400SB0025ham005 | - 6 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | supporting documentation for those rebate agreements, grants, |
| 2 | | and contracts to the utility. The Department is authorized to |
| 3 | | adopt any rules necessary and prescribe procedures in order to |
| 4 | | ensure compliance by applicants in carrying out the purposes |
| 5 | | of rebate agreements for energy efficiency measures |
| 6 | | implemented by the Department made under this Section. |
| 7 | | The details of the measures implemented by the Department |
| 8 | | shall be submitted by the Department to the Commission in |
| 9 | | connection with the utility's filing regarding the energy |
| 10 | | efficiency measures that the utility implements. |
| 11 | | The portfolio of measures, administered by both the |
| 12 | | utilities and the Department, shall, in combination, be |
| 13 | | designed to achieve the annual energy savings requirements set |
| 14 | | forth in subsection (c) of this Section, as modified by |
| 15 | | subsection (d) of this Section. |
| 16 | | The utility and the Department shall agree upon a |
| 17 | | reasonable portfolio of measures and determine the measurable |
| 18 | | corresponding percentage of the savings goals associated with |
| 19 | | measures implemented by the Department. |
| 20 | | No utility shall be assessed a penalty under subsection |
| 21 | | (f) of this Section for failure to make a timely filing if that |
| 22 | | failure is the result of a lack of agreement with the |
| 23 | | Department with respect to the allocation of responsibilities |
| 24 | | or related costs or target assignments. In that case, the |
| 25 | | Department and the utility shall file their respective plans |
| 26 | | with the Commission and the Commission shall determine an |
|
| | 10400SB0025ham005 | - 7 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | appropriate division of measures and programs that meets the |
| 2 | | requirements of this Section. |
| 3 | | (e-5) The provisions of this subsection (e-5) shall be |
| 4 | | applicable to those multi-year plans that commence after |
| 5 | | December 31, 2017. Natural gas utilities shall be responsible |
| 6 | | for overseeing the design, development, and filing of their |
| 7 | | efficiency plans with the Commission and may outsource |
| 8 | | development and implementation of energy efficiency measures. |
| 9 | | A minimum of 10% of the entire portfolio of cost-effective |
| 10 | | energy efficiency measures shall be procured from local |
| 11 | | government, municipal corporations, school districts, public |
| 12 | | institutions of higher education, and community college |
| 13 | | districts; unless a utility files a plan or amended plan under |
| 14 | | the provisions of subsection (e-20), in which case the minimum |
| 15 | | spend for measures from such public customers shall be equal |
| 16 | | to at least 30% of non-residential spending. Five percent of |
| 17 | | the entire portfolio of cost-effective energy efficiency |
| 18 | | measures may be granted to local government and municipal |
| 19 | | corporations for market transformation initiatives. |
| 20 | | Through calendar year 2026, the The utilities shall also |
| 21 | | present a portfolio of energy efficiency measures |
| 22 | | proportionate to the share of total annual utility revenues in |
| 23 | | Illinois from households at or below 150% of the poverty |
| 24 | | level. Such programs shall be targeted to households with |
| 25 | | incomes at or below 80% of area median income. |
| 26 | | (e-7) Beginning January 1, 2027, the following |
|
| | 10400SB0025ham005 | - 8 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | requirements shall be in effect for efficiency programs |
| 2 | | targeted to low-income households. For the purposes of this |
| 3 | | Section, "low-income households" means households with incomes |
| 4 | | at or below 80% of the area median income. Utilities shall |
| 5 | | leverage existing State and federal low-income weatherization |
| 6 | | programs and delivery capacity to the extent practicable. |
| 7 | | Utilities shall also prioritize contracting with |
| 8 | | organizations, government agencies, and businesses with a |
| 9 | | track record of delivering weatherization services in |
| 10 | | low-income communities in this State to deliver any low-income |
| 11 | | programs that are not integrated with State and federal |
| 12 | | low-income weatherization programs. |
| 13 | | (e-8) Beginning January 1, 2027, the following |
| 14 | | requirements shall be in effect for efficiency programs |
| 15 | | targeted to low-income households, except for single-fuel gas |
| 16 | | utilities with less than 1,000,000 customers: |
| 17 | | (1) The portion of the entire budget for efficiency |
| 18 | | programs that is spent on efficiency programs for |
| 19 | | low-income households shall be no less than the greater |
| 20 | | of: (A) 25% or (B) five percentage points more than the |
| 21 | | proportion of total annual gas sales to non-opt-out retail |
| 22 | | customers that are consumed by low-income households. |
| 23 | | (2) The portion of spending on efficiency measures |
| 24 | | that are targeted to low-income households that is |
| 25 | | delivered through whole building weatherization programs |
| 26 | | that comprehensively address building envelope efficiency |
|
| | 10400SB0025ham005 | - 9 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | upgrade opportunities as well as other efficiency measures |
| 2 | | shall be at least 80%. |
| 3 | | (3) Utilities shall invest in health and safety |
| 4 | | measures that are appropriate and necessary for |
| 5 | | comprehensively weatherizing the single-family and |
| 6 | | multi-family buildings of low-income households, with up |
| 7 | | to 15% of income-qualified program spending made available |
| 8 | | for such purposes. |
| 9 | | (e-10) A utility providing approved energy efficiency |
| 10 | | measures in this State shall be permitted to recover costs of |
| 11 | | those measures through an automatic adjustment clause tariff |
| 12 | | filed with and approved by the Commission. The tariff shall be |
| 13 | | established outside the context of a general rate case and |
| 14 | | shall be applicable to the utility's customers other than the |
| 15 | | customers described in subsection (m) of this Section. Each |
| 16 | | year the Commission shall initiate a review to reconcile any |
| 17 | | amounts collected with the actual costs and to determine the |
| 18 | | required adjustment to the annual tariff factor to match |
| 19 | | annual expenditures. |
| 20 | | (e-15) For those multi-year plans that commence prior to |
| 21 | | January 1, 2018, each utility shall include, in its recovery |
| 22 | | of costs, the costs estimated for both the utility's and the |
| 23 | | Department's implementation of energy efficiency measures. |
| 24 | | Costs collected by the utility for measures implemented by the |
| 25 | | Department shall be submitted to the Department pursuant to |
| 26 | | Section 605-323 of the Civil Administrative Code of Illinois, |
|
| | 10400SB0025ham005 | - 10 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | shall be deposited into the Energy Efficiency Portfolio |
| 2 | | Standards Fund, and shall be used by the Department solely for |
| 3 | | the purpose of implementing these measures. A utility shall |
| 4 | | not be required to advance any moneys to the Department but |
| 5 | | only to forward such funds as it has collected. The Department |
| 6 | | shall report to the Commission on an annual basis regarding |
| 7 | | the costs actually incurred by the Department in the |
| 8 | | implementation of the measures. Any changes to the costs of |
| 9 | | energy efficiency measures as a result of plan modifications |
| 10 | | shall be appropriately reflected in amounts recovered by the |
| 11 | | utility and turned over to the Department. |
| 12 | | (e-20) The provisions of this Section shall be applicable |
| 13 | | to multi-year plans that commence after the effective date of |
| 14 | | this amendatory Act of the 104th General Assembly and are |
| 15 | | submitted by single fuel service utilities on or before the |
| 16 | | effective date of this amendatory Act of the 104th General |
| 17 | | Assembly. A natural gas utility may propose, as part of its |
| 18 | | submission of a multi-year plan, to increase the amount of |
| 19 | | energy efficiency implemented in any multi-year planning |
| 20 | | period above the level that can be achieved under the spending |
| 21 | | cap set forth in subsection (d) of this Section. The first plan |
| 22 | | to increase energy efficiency may be submitted as an amendment |
| 23 | | to the utility's plan for calendar years 2027 through 2029, |
| 24 | | but any amended plans must be filed with the Commission by |
| 25 | | March 1, 2026 or the effective date of this amendatory Act of |
| 26 | | the 104th General Assembly, whichever is later. In addition to |
|
| | 10400SB0025ham005 | - 11 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | the policy goals established in subsection (f), the Commission |
| 2 | | shall consider, in determining the appropriateness of a |
| 3 | | proposal, whether the multi-year plan at a minimum: |
| 4 | | (1) identifies a cost-effective portfolio of measures |
| 5 | | and specifies the natural gas savings that are reasonably |
| 6 | | likely to be achieved by the utility; |
| 7 | | (2) demonstrates that the plan or modified plan, at a |
| 8 | | minimum, will result in a portfolio of energy efficiency |
| 9 | | measures that will provide more natural gas savings than |
| 10 | | would have been achieved in a plan subject to subsection |
| 11 | | (c); |
| 12 | | (3) demonstrates that the plan reflects efforts to |
| 13 | | coordinate delivery of electric utility efficiency |
| 14 | | programs where such coordination can reduce costs, |
| 15 | | increase effectiveness of outreach to customers, and |
| 16 | | increase savings. A gas utility may count electricity |
| 17 | | savings toward its gas efficiency savings goals subject to |
| 18 | | the following limitations: |
| 19 | | (A) only electricity savings produced as a result |
| 20 | | of the installation of a gas efficiency measure, such |
| 21 | | as reductions in electricity consumption by gas |
| 22 | | furnace fans and electric air conditioners that |
| 23 | | results from the installation of insulation measures |
| 24 | | that reduce gas used for space heating, may be |
| 25 | | counted; |
| 26 | | (B) such electricity savings may only be counted |
|
| | 10400SB0025ham005 | - 12 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | when they are generated in service territories not |
| 2 | | served by electric utilities subject to Section |
| 3 | | 8-103B; |
| 4 | | (C) no more than 5% of the total savings claimed |
| 5 | | toward a gas utility's savings goal may be from such |
| 6 | | electricity savings. For the purposes of this Section, |
| 7 | | a kilowatt-hour of savings is equal to 0.03412 gas |
| 8 | | therms; |
| 9 | | (4) demonstrates whether an increase in funding is |
| 10 | | necessary to meet the proposed increase in the amount of |
| 11 | | energy efficiency; |
| 12 | | (5) prioritizes income-qualified measures and |
| 13 | | weatherization measures; and |
| 14 | | (6) demonstrates that the multi-year plan strikes a |
| 15 | | reasonable balance between the goals of the following: |
| 16 | | (A) increasing cost-effective efficiency savings |
| 17 | | and related greenhouse gas emission reductions; |
| 18 | | (B) reducing overall gas system costs, recognizing |
| 19 | | that efficiency investments reduce usage and, in turn, |
| 20 | | the potential need for system investments over the |
| 21 | | long-term; |
| 22 | | (C) increasing energy affordability, especially |
| 23 | | for low-income customers; |
| 24 | | (D) within the residential sector, prioritizing |
| 25 | | investment in weatherization and other measures that |
| 26 | | reduce heating loads over gas equipment measures; and |
|
| | 10400SB0025ham005 | - 13 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | (E) providing a diverse cross-section of |
| 2 | | opportunities for customers of all rate classes to |
| 3 | | participate in efficiency programs. |
| 4 | | For single-fuel gas utilities with less than 1,000,000 |
| 5 | | customers, the following requirements shall be in effect for |
| 6 | | efficiency programs targeted to low-income households: |
| 7 | | (1) For gas utilities with greater than 300,000 |
| 8 | | customers, the portion of the entire budget for efficiency |
| 9 | | programs that is spent on efficiency programs for |
| 10 | | low-income households shall be no less than the greater of |
| 11 | | (A) 25% or (B) five percentage points more than the |
| 12 | | proportion of total annual gas sales to non-opt-out retail |
| 13 | | customers that are consumed by low-income households. For |
| 14 | | gas utilities with 300,000 or fewer customers, the portion |
| 15 | | of the entire budget for efficiency programs that is spent |
| 16 | | on efficiency programs for low-income households shall be |
| 17 | | no less than the greater of (A) 15% or (B) five percentage |
| 18 | | points more than the proportion of total annual gas sales |
| 19 | | to non-opt-out retail customers that are consumed by |
| 20 | | low-income households. |
| 21 | | (2) The portion of spending on efficiency measures |
| 22 | | targeted to low-income households that shall be delivered |
| 23 | | through whole building weatherization programs that |
| 24 | | comprehensively address building envelope efficiency |
| 25 | | upgrade opportunities as well as other efficiency measures |
| 26 | | shall be at least 80%. |
|
| | 10400SB0025ham005 | - 14 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | (3) Utilities shall invest in health and safety |
| 2 | | measures appropriate and necessary for comprehensively |
| 3 | | weatherizing the single-family and multi-family buildings |
| 4 | | of low-income households, with up to 15% of |
| 5 | | income-qualified program spending made available for such |
| 6 | | purposes. |
| 7 | | As part of its order approving the plan or modified plan, |
| 8 | | the Commission is authorized to: |
| 9 | | (1) adjust the limitation on the amount of energy |
| 10 | | efficiency measures implemented pursuant to subsection (d) |
| 11 | | to the extent necessary to meet the increase in the amount |
| 12 | | of energy efficiency approved by the Commission pursuant |
| 13 | | to this subsection (e-20); |
| 14 | | (2) adjust the public sector spending requirements |
| 15 | | pursuant to subsection (e-5); |
| 16 | | (3) adopt an incentive mechanism for the utility to |
| 17 | | meet or exceed the goals associated with its proposed |
| 18 | | multi-year plan if the utility meets or exceeds the |
| 19 | | following minimum requirements: |
| 20 | | (A) the utility proposes a plan budget over the |
| 21 | | applicable multi-year period that is equal to or |
| 22 | | greater than 5% of the amounts paid by non-opt-out |
| 23 | | retail customers in connection with natural gas |
| 24 | | service in the applicable multi-year period; |
| 25 | | (B) for efficiency program years 2027 through |
| 26 | | 2029, the utility achieves average incremental annual |
|
| | 10400SB0025ham005 | - 15 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | savings of at least 0.7% of total average annual gas |
| 2 | | sales to non-opt-out retail customers over the years |
| 3 | | 2023 through 2025. For multi-year efficiency program |
| 4 | | plans beginning after 2029, achieving average |
| 5 | | incremental annual savings of at least 0.8% of total |
| 6 | | average annual gas sales to non-opt-out retail |
| 7 | | customers during the 3-year period ending 2 years |
| 8 | | prior to the first year of the plan. In all multi-year |
| 9 | | periods, the minimum incremental annual savings |
| 10 | | requirement shall be reduced by 0.01 percentage points |
| 11 | | for every 1 percentage point increase in low-income or |
| 12 | | moderate-income spending above the minimum levels |
| 13 | | required by subsection (e-5). In no event shall the |
| 14 | | minimum incremental annual savings requirement be |
| 15 | | reduced by more than 0.10 percentage points even if |
| 16 | | low-income or moderate-income spending is increased by |
| 17 | | more than 10 percentage points above the minimum |
| 18 | | levels required by subsection (e-5). The Commission |
| 19 | | may reduce the magnitude of the minimum savings |
| 20 | | requirements under this subparagraph (B) if the |
| 21 | | utility can demonstrate that it is not possible to |
| 22 | | achieve them with a budget equal to 5% of revenues from |
| 23 | | eligible customers while meeting other minimum |
| 24 | | requirements. If a utility attempts to demonstrate |
| 25 | | that it cannot meet the minimum savings requirements |
| 26 | | in this paragraph with a budget equal to 5% of revenues |
|
| | 10400SB0025ham005 | - 16 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | from eligible customers, and the Commission finds that |
| 2 | | the utility has not made a sufficiently compelling |
| 3 | | demonstration, the utility may withdraw its plan and |
| 4 | | file a revised plan; |
| 5 | | (C) the utility achieves an average savings life |
| 6 | | of at least 12 years. Average savings lives may be |
| 7 | | shorter than the average operational lives of measures |
| 8 | | if the measures do not produce savings in every year in |
| 9 | | which they operate or if the savings that measures |
| 10 | | produce decline during their operational lives; and |
| 11 | | (D) the utility spends at least 67% of all |
| 12 | | financial incentive dollars on efficiency measures |
| 13 | | that (1) reduce the space heating loads of buildings |
| 14 | | through improvements such as to building envelopes, |
| 15 | | ventilation systems, space heating distribution |
| 16 | | systems, and space heating system controls; (2) reduce |
| 17 | | the water heating loads of buildings such as through |
| 18 | | insulation of hot water pipes, recovery and reuse of |
| 19 | | heat from waste water and reductions in the amount of |
| 20 | | hot water required to meet customer needs; or (3) |
| 21 | | reduce the process heat loads of industrial |
| 22 | | facilities. Any spending on health and safety measures |
| 23 | | shall count toward this requirement. No financial |
| 24 | | incentive spending on furnaces, boilers, water |
| 25 | | heaters, and other gas-consuming equipment may be |
| 26 | | counted toward this requirement; and |
|
| | 10400SB0025ham005 | - 17 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | (4) for modified plans, require a compliance filing |
| 2 | | from the utility to adjust budgets and natural gas savings |
| 3 | | targets, if necessary, to reflect the final level of |
| 4 | | customers opting out under subsection (m-1). |
| 5 | | For the purposes of this subsection (e-20): |
| 6 | | "Average savings life" means (i) the savings that will be |
| 7 | | realized as a result of a utility's efficiency programs over |
| 8 | | the lives of all efficiency measures divided by (ii) the |
| 9 | | savings that will be produced in the first year after such |
| 10 | | measures are installed. |
| 11 | | "Moderate-income" means income between 80% of area median |
| 12 | | income and 300% of the federal poverty limit. |
| 13 | | (f) No later than October 1, 2010, each gas utility shall |
| 14 | | file an energy efficiency plan with the Commission to meet the |
| 15 | | energy efficiency standards through May 31, 2014. No later |
| 16 | | than October 1, 2013, each gas utility shall file an energy |
| 17 | | efficiency plan with the Commission to meet the energy |
| 18 | | efficiency standards through May 31, 2017. Beginning in 2017 |
| 19 | | and every 4 years thereafter, each utility shall file an |
| 20 | | energy efficiency plan with the Commission to meet the energy |
| 21 | | efficiency standards for the next applicable 4-year period |
| 22 | | beginning January 1 of the year following the filing. For |
| 23 | | those multi-year plans commencing on January 1, 2018, each |
| 24 | | utility shall file its proposed energy efficiency plan no |
| 25 | | later than 30 days after the effective date of this amendatory |
| 26 | | Act of the 99th General Assembly or May 1, 2017, whichever is |
|
| | 10400SB0025ham005 | - 18 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | later. Beginning in 2021 and every 4 years thereafter, each |
| 2 | | utility shall file its energy efficiency plan no later than |
| 3 | | March 1. If a utility does not file such a plan on or before |
| 4 | | the applicable filing deadline for the plan, then it shall |
| 5 | | face a penalty of $100,000 per day until the plan is filed. |
| 6 | | Each utility's plan shall set forth the utility's |
| 7 | | proposals to meet the utility's portion of the energy |
| 8 | | efficiency standards identified in subsection (c) of this |
| 9 | | Section, as modified by subsection (d) of this Section, taking |
| 10 | | into account the unique circumstances of the utility's service |
| 11 | | territory. For those plans commencing after December 31, 2021, |
| 12 | | the Commission shall seek public comment on the utility's plan |
| 13 | | and shall issue an order approving or disapproving each plan |
| 14 | | within 6 months after its submission. For those plans |
| 15 | | commencing on January 1, 2018, the Commission shall seek |
| 16 | | public comment on the utility's plan and shall issue an order |
| 17 | | approving or disapproving each plan no later than August 31, |
| 18 | | 2017, or 105 days after the effective date of this amendatory |
| 19 | | Act of the 99th General Assembly, whichever is later. If the |
| 20 | | Commission disapproves a plan, the Commission shall, within 30 |
| 21 | | days, describe in detail the reasons for the disapproval and |
| 22 | | describe a path by which the utility may file a revised draft |
| 23 | | of the plan to address the Commission's concerns |
| 24 | | satisfactorily. If the utility does not refile with the |
| 25 | | Commission within 60 days after the disapproval, the utility |
| 26 | | shall be subject to penalties at a rate of $100,000 per day |
|
| | 10400SB0025ham005 | - 19 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | until the plan is filed. This process shall continue, and |
| 2 | | penalties shall accrue, until the utility has successfully |
| 3 | | filed a portfolio of energy efficiency measures. Penalties |
| 4 | | shall be deposited into the Energy Efficiency Trust Fund and |
| 5 | | the cost of any such penalties may not be recovered from |
| 6 | | ratepayers. In submitting proposed energy efficiency plans and |
| 7 | | funding levels to meet the savings goals adopted by this Act |
| 8 | | the utility shall: |
| 9 | | (1) Demonstrate that its proposed energy efficiency |
| 10 | | measures will achieve the requirements that are identified |
| 11 | | in subsection (c) of this Section, as modified by |
| 12 | | subsection (d) of this Section. |
| 13 | | (2) Present specific proposals to implement new |
| 14 | | building and appliance standards that have been placed |
| 15 | | into effect. |
| 16 | | (3) Present estimates of the total amount paid for gas |
| 17 | | service expressed on a per therm basis associated with the |
| 18 | | proposed portfolio of measures designed to meet the |
| 19 | | requirements that are identified in subsection (c) of this |
| 20 | | Section, as modified by subsection (d) of this Section. |
| 21 | | (4) For those multi-year plans that commence prior to |
| 22 | | January 1, 2018, coordinate with the Department to present |
| 23 | | a portfolio of energy efficiency measures proportionate to |
| 24 | | the share of total annual utility revenues in Illinois |
| 25 | | from households at or below 150% of the poverty level. |
| 26 | | Such programs shall be targeted to households with incomes |
|
| | 10400SB0025ham005 | - 20 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | at or below 80% of area median income. |
| 2 | | (5) Demonstrate that its overall portfolio of energy |
| 3 | | efficiency measures, not including low-income programs |
| 4 | | described in item (4) of this subsection (f) and |
| 5 | | subsection (e-5) of this Section, are cost-effective using |
| 6 | | the total resource cost test and represent a diverse cross |
| 7 | | section of opportunities for customers of all rate classes |
| 8 | | to participate in the programs. |
| 9 | | (6) Demonstrate that a gas utility affiliated with an |
| 10 | | electric utility that is required to comply with Section |
| 11 | | 8-103 or 8-103B of this Act has integrated gas and |
| 12 | | electric efficiency measures into a single program that |
| 13 | | reduces program or participant costs and appropriately |
| 14 | | allocates costs to gas and electric ratepayers. For those |
| 15 | | multi-year plans that commence prior to January 1, 2018, |
| 16 | | the Department shall integrate all gas and electric |
| 17 | | programs it delivers in any such utilities' service |
| 18 | | territories, unless the Department can show that |
| 19 | | integration is not feasible or appropriate. |
| 20 | | (7) Include a proposed cost recovery tariff mechanism |
| 21 | | to fund the proposed energy efficiency measures and to |
| 22 | | ensure the recovery of the prudently and reasonably |
| 23 | | incurred costs of Commission-approved programs. |
| 24 | | (8) Provide for quarterly status reports tracking |
| 25 | | implementation of and expenditures for the utility's |
| 26 | | portfolio of measures and, if applicable, the Department's |
|
| | 10400SB0025ham005 | - 21 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | portfolio of measures, an annual independent review, and a |
| 2 | | full independent evaluation of the multi-year results of |
| 3 | | the performance and the cost-effectiveness of the |
| 4 | | utility's and, if applicable, Department's portfolios of |
| 5 | | measures and broader net program impacts and, to the |
| 6 | | extent practical, for adjustment of the measures on a |
| 7 | | going forward basis as a result of the evaluations. The |
| 8 | | resources dedicated to evaluation shall not exceed 3% of |
| 9 | | portfolio resources in any given multi-year period. |
| 10 | | (g) No more than 3% of expenditures on energy efficiency |
| 11 | | measures may be allocated for demonstration of breakthrough |
| 12 | | equipment and devices. |
| 13 | | (h) Illinois natural gas utilities that are affiliated by |
| 14 | | virtue of a common parent company may, at the utilities' |
| 15 | | request, be considered a single natural gas utility for |
| 16 | | purposes of complying with this Section. |
| 17 | | (i) If, after 3 years, a gas utility fails to meet the |
| 18 | | efficiency standard specified in subsection (c) of this |
| 19 | | Section as modified by subsection (d), then it shall make a |
| 20 | | contribution to the Low-Income Home Energy Assistance Program. |
| 21 | | The total liability for failure to meet the goal shall be |
| 22 | | assessed as follows: |
| 23 | | (1) a large gas utility shall pay $600,000; |
| 24 | | (2) a medium gas utility shall pay $400,000; and |
| 25 | | (3) a small gas utility shall pay $200,000. |
| 26 | | For purposes of this Section, (i) a "large gas utility" is |
|
| | 10400SB0025ham005 | - 22 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | a gas utility that on December 31, 2008, served more than |
| 2 | | 1,500,000 gas customers in Illinois; (ii) a "medium gas |
| 3 | | utility" is a gas utility that on December 31, 2008, served |
| 4 | | fewer than 1,500,000, but more than 500,000 gas customers in |
| 5 | | Illinois; and (iii) a "small gas utility" is a gas utility that |
| 6 | | on December 31, 2008, served fewer than 500,000 and more than |
| 7 | | 100,000 gas customers in Illinois. The costs of this |
| 8 | | contribution may not be recovered from ratepayers. |
| 9 | | If a gas utility fails to meet the efficiency standard |
| 10 | | specified in subsection (c) of this Section, as modified by |
| 11 | | subsection (d) of this Section, in any 2 consecutive |
| 12 | | multi-year planning periods, then the responsibility for |
| 13 | | implementing the utility's energy efficiency measures shall be |
| 14 | | transferred to an independent program administrator selected |
| 15 | | by the Commission. Reasonable and prudent costs incurred by |
| 16 | | the independent program administrator to meet the efficiency |
| 17 | | standard specified in subsection (c) of this Section, as |
| 18 | | modified by subsection (d) of this Section, may be recovered |
| 19 | | from the customers of the affected gas utilities, other than |
| 20 | | customers described in subsection (m) of this Section. The |
| 21 | | utility shall provide the independent program administrator |
| 22 | | with all information and assistance necessary to perform the |
| 23 | | program administrator's duties including but not limited to |
| 24 | | customer, account, and energy usage data, and shall allow the |
| 25 | | program administrator to include inserts in customer bills. |
| 26 | | The utility may recover reasonable costs associated with any |
|
| | 10400SB0025ham005 | - 23 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | such assistance. |
| 2 | | (j) No utility shall be deemed to have failed to meet the |
| 3 | | energy efficiency standards to the extent any such failure is |
| 4 | | due to a failure of the Department. |
| 5 | | (k) Not later than January 1, 2012, the Commission shall |
| 6 | | develop and solicit public comment on a plan to foster |
| 7 | | statewide coordination and consistency between statutorily |
| 8 | | mandated natural gas and electric energy efficiency programs |
| 9 | | to reduce program or participant costs or to improve program |
| 10 | | performance. Not later than September 1, 2013, the Commission |
| 11 | | shall issue a report to the General Assembly containing its |
| 12 | | findings and recommendations. |
| 13 | | (l) This Section does not apply to a gas utility that on |
| 14 | | January 1, 2009, provided gas service to fewer than 100,000 |
| 15 | | customers in Illinois. |
| 16 | | (m) Subsections (a) through (k) of this Section do not |
| 17 | | apply to customers of a natural gas utility that have a North |
| 18 | | American Industry Classification System code number that is |
| 19 | | 22111 or any such code number beginning with the digits 31, 32, |
| 20 | | or 33 and (i) annual usage in the aggregate of 4 million therms |
| 21 | | or more within the service territory of the affected gas |
| 22 | | utility or with aggregate usage of 8 million therms or more in |
| 23 | | this State and complying with the provisions of item (l) of |
| 24 | | this subsection (m); or (ii) using natural gas as feedstock |
| 25 | | and meeting the usage requirements described in item (i) of |
| 26 | | this subsection (m), to the extent such annual feedstock usage |
|
| | 10400SB0025ham005 | - 24 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | is greater than 60% of the customer's total annual usage of |
| 2 | | natural gas. |
| 3 | | (1) Customers described in this subsection (m) of this |
| 4 | | Section shall apply, on a form approved on or before |
| 5 | | October 1, 2009 by the Department, to the Department to be |
| 6 | | designated as a self-directing customer ("SDC") or as an |
| 7 | | exempt customer using natural gas as a feedstock from |
| 8 | | which other products are made, including, but not limited |
| 9 | | to, feedstock for a hydrogen plant, on or before the 1st |
| 10 | | day of February, 2010. Thereafter, application may be made |
| 11 | | not less than 6 months before the filing date of the gas |
| 12 | | utility energy efficiency plan described in subsection (f) |
| 13 | | of this Section; however, a new customer that commences |
| 14 | | taking service from a natural gas utility after February |
| 15 | | 1, 2010 may apply to become a SDC or exempt customer up to |
| 16 | | 30 days after beginning service. Customers described in |
| 17 | | this subsection (m) that have not already been approved by |
| 18 | | the Department may apply to be designated a self-directing |
| 19 | | customer or exempt customer, on a form approved by the |
| 20 | | Department, between September 1, 2013 and September 30, |
| 21 | | 2013. Customer applications that are approved by the |
| 22 | | Department under this amendatory Act of the 98th General |
| 23 | | Assembly shall be considered to be a self-directing |
| 24 | | customer or exempt customer, as applicable, for the |
| 25 | | current 3-year planning period effective December 1, 2013. |
| 26 | | Such application shall contain the following: |
|
| | 10400SB0025ham005 | - 25 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | (A) the customer's certification that, at the time |
| 2 | | of its application, it qualifies to be a SDC or exempt |
| 3 | | customer described in this subsection (m) of this |
| 4 | | Section; |
| 5 | | (B) in the case of a SDC, the customer's |
| 6 | | certification that it has established or will |
| 7 | | establish by the beginning of the utility's multi-year |
| 8 | | planning period commencing subsequent to the |
| 9 | | application, and will maintain for accounting |
| 10 | | purposes, an energy efficiency reserve account and |
| 11 | | that the customer will accrue funds in said account to |
| 12 | | be held for the purpose of funding, in whole or in |
| 13 | | part, energy efficiency measures of the customer's |
| 14 | | choosing, which may include, but are not limited to, |
| 15 | | projects involving combined heat and power systems |
| 16 | | that use the same energy source both for the |
| 17 | | generation of electrical or mechanical power and the |
| 18 | | production of steam or another form of useful thermal |
| 19 | | energy or the use of combustible gas produced from |
| 20 | | biomass, or both; |
| 21 | | (C) in the case of a SDC, the customer's |
| 22 | | certification that annual funding levels for the |
| 23 | | energy efficiency reserve account will be equal to 2% |
| 24 | | of the customer's cost of natural gas, composed of the |
| 25 | | customer's commodity cost and the delivery service |
| 26 | | charges paid to the gas utility, or $150,000, |
|
| | 10400SB0025ham005 | - 26 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | whichever is less; |
| 2 | | (D) in the case of a SDC, the customer's |
| 3 | | certification that the required reserve account |
| 4 | | balance will be capped at 3 years' worth of accruals |
| 5 | | and that the customer may, at its option, make further |
| 6 | | deposits to the account to the extent such deposit |
| 7 | | would increase the reserve account balance above the |
| 8 | | designated cap level; |
| 9 | | (E) in the case of a SDC, the customer's |
| 10 | | certification that by October 1 of each year, |
| 11 | | beginning no sooner than October 1, 2012, the customer |
| 12 | | will report to the Department information, for the |
| 13 | | 12-month period ending May 31 of the same year, on all |
| 14 | | deposits and reductions, if any, to the reserve |
| 15 | | account during the reporting year, and to the extent |
| 16 | | deposits to the reserve account in any year are in an |
| 17 | | amount less than $150,000, the basis for such reduced |
| 18 | | deposits; reserve account balances by month; a |
| 19 | | description of energy efficiency measures undertaken |
| 20 | | by the customer and paid for in whole or in part with |
| 21 | | funds from the reserve account; an estimate of the |
| 22 | | energy saved, or to be saved, by the measure; and that |
| 23 | | the report shall include a verification by an officer |
| 24 | | or plant manager of the customer or by a registered |
| 25 | | professional engineer or certified energy efficiency |
| 26 | | trade professional that the funds withdrawn from the |
|
| | 10400SB0025ham005 | - 27 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | reserve account were used for the energy efficiency |
| 2 | | measures; |
| 3 | | (F) in the case of an exempt customer, the |
| 4 | | customer's certification of the level of gas usage as |
| 5 | | feedstock in the customer's operation in a typical |
| 6 | | year and that it will provide information establishing |
| 7 | | this level, upon request of the Department; |
| 8 | | (G) in the case of either an exempt customer or a |
| 9 | | SDC, the customer's certification that it has provided |
| 10 | | the gas utility or utilities serving the customer with |
| 11 | | a copy of the application as filed with the |
| 12 | | Department; |
| 13 | | (H) in the case of either an exempt customer or a |
| 14 | | SDC, certification of the natural gas utility or |
| 15 | | utilities serving the customer in Illinois including |
| 16 | | the natural gas utility accounts that are the subject |
| 17 | | of the application; and |
| 18 | | (I) in the case of either an exempt customer or a |
| 19 | | SDC, a verification signed by a plant manager or an |
| 20 | | authorized corporate officer attesting to the |
| 21 | | truthfulness and accuracy of the information contained |
| 22 | | in the application. |
| 23 | | (2) The Department shall review the application to |
| 24 | | determine that it contains the information described in |
| 25 | | provisions (A) through (I) of item (1) of this subsection |
| 26 | | (m), as applicable. The review shall be completed within |
|
| | 10400SB0025ham005 | - 28 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | 30 days after the date the application is filed with the |
| 2 | | Department. Absent a determination by the Department |
| 3 | | within the 30-day period, the applicant shall be |
| 4 | | considered to be a SDC or exempt customer, as applicable, |
| 5 | | for all subsequent multi-year planning periods, as of the |
| 6 | | date of filing the application described in this |
| 7 | | subsection (m). If the Department determines that the |
| 8 | | application does not contain the applicable information |
| 9 | | described in provisions (A) through (I) of item (1) of |
| 10 | | this subsection (m), it shall notify the customer, in |
| 11 | | writing, of its determination that the application does |
| 12 | | not contain the required information and identify the |
| 13 | | information that is missing, and the customer shall |
| 14 | | provide the missing information within 15 working days |
| 15 | | after the date of receipt of the Department's |
| 16 | | notification. |
| 17 | | (3) The Department shall have the right to audit the |
| 18 | | information provided in the customer's application and |
| 19 | | annual reports to ensure continued compliance with the |
| 20 | | requirements of this subsection. Based on the audit, if |
| 21 | | the Department determines the customer is no longer in |
| 22 | | compliance with the requirements of items (A) through (I) |
| 23 | | of item (1) of this subsection (m), as applicable, the |
| 24 | | Department shall notify the customer in writing of the |
| 25 | | noncompliance. The customer shall have 30 days to |
| 26 | | establish its compliance, and failing to do so, may have |
|
| | 10400SB0025ham005 | - 29 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | its status as a SDC or exempt customer revoked by the |
| 2 | | Department. The Department shall treat all information |
| 3 | | provided by any customer seeking SDC status or exemption |
| 4 | | from the provisions of this Section as strictly |
| 5 | | confidential. |
| 6 | | (4) Upon request, or on its own motion, the Commission |
| 7 | | may open an investigation, no more than once every 3 years |
| 8 | | and not before October 1, 2014, to evaluate the |
| 9 | | effectiveness of the self-directing program described in |
| 10 | | this subsection (m). |
| 11 | | Customers described in this subsection (m) that applied to |
| 12 | | the Department on January 3, 2013, were approved by the |
| 13 | | Department on February 13, 2013 to be a self-directing |
| 14 | | customer or exempt customer, and receive natural gas from a |
| 15 | | utility that provides gas service to at least 500,000 retail |
| 16 | | customers in Illinois and electric service to at least |
| 17 | | 1,000,000 retail customers in Illinois shall be considered to |
| 18 | | be a self-directing customer or exempt customer, as |
| 19 | | applicable, for the current 3-year planning period effective |
| 20 | | December 1, 2013. |
| 21 | | (m-1) For utilities that file an amended plan for the |
| 22 | | period covering calendar years 2027 through 2029, and for all |
| 23 | | utilities for all calendar years covered by a multi-year plan |
| 24 | | commencing on or after January 1, 2030, subsections (a) |
| 25 | | through (k) of this Section do not apply to eligible customers |
| 26 | | of a natural gas utility that have chosen to opt out of |
|
| | 10400SB0025ham005 | - 30 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | multi-year plans. |
| 2 | | (1) For purposes of this subsection (m-1), "eligible |
| 3 | | customer" means any retail customer of a natural gas |
| 4 | | utility, except for federal, State, municipal and other |
| 5 | | public customers, with a North American Industry |
| 6 | | Classification System code number that is 22111 or any |
| 7 | | such code number beginning with the digits 31, 32, or 33 |
| 8 | | and (i) annual usage in the aggregate of 4,000,000 therms |
| 9 | | or more within the service territory of the affected gas |
| 10 | | utility or with aggregate usage of 8,000,000 therms or |
| 11 | | more in this State; or (ii) using natural gas as feedstock |
| 12 | | and meeting the usage requirements described in item (i) |
| 13 | | of this paragraph (1), to the extent such annual feedstock |
| 14 | | usage is greater than 60% of the customer's total annual |
| 15 | | usage of natural gas. A determination of whether this |
| 16 | | subsection is applicable to a customer shall be made for |
| 17 | | each multi-year plan beginning after January 1, 2026. The |
| 18 | | criteria for determining whether this subsection is |
| 19 | | applicable shall be the 12 consecutive billing periods |
| 20 | | prior to the start of the first year of each such |
| 21 | | multi-year plan. |
| 22 | | (2) Within 45 days after the effective date of this |
| 23 | | amendatory Act of the 104th General Assembly, the |
| 24 | | Commission shall prescribe the form for notice required |
| 25 | | for opting out of energy efficiency programs. Within 120 |
| 26 | | days after the Commission's initial issuance of the form |
|
| | 10400SB0025ham005 | - 31 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | for notice, customers described in paragraph (1) of this |
| 2 | | subsection (m-1) may submit completed forms to the natural |
| 3 | | gas utility. Thereafter, forms must be submitted to the |
| 4 | | natural gas utility not less than 6 months before the |
| 5 | | filing date of the gas utility energy efficiency plan |
| 6 | | described in subsection (f) of this Section; however, a |
| 7 | | new customer that commences taking service from a natural |
| 8 | | gas utility after January 1, 2026 may submit a form up to |
| 9 | | 30 days after beginning service. The form for notice for |
| 10 | | opting out of natural gas energy efficiency programs shall |
| 11 | | contain the following: |
| 12 | | (A) a statement indicating that the customer has |
| 13 | | elected to opt-out; |
| 14 | | (B) the account numbers for the customer accounts |
| 15 | | to which the opt out shall apply; |
| 16 | | (C) the mailing address associated with each |
| 17 | | customer account identified under subparagraph (B); |
| 18 | | (D) the customer's certification that, at the time |
| 19 | | its form was submitted, it qualifies as an eligible |
| 20 | | customer, as described in paragraph (1) of this |
| 21 | | subsection (m-1); |
| 22 | | (E) an American Society of Heating, Refrigerating, |
| 23 | | and Air Conditioning Engineers (ASHRAE) level 2 or |
| 24 | | higher audit report conducted by an independent |
| 25 | | third-party expert identifying cost-effective energy |
| 26 | | efficiency project opportunities that could be |
|
| | 10400SB0025ham005 | - 32 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | invested in over the next 10 years. A customer with a |
| 2 | | specialized process may use a self-audit process in |
| 3 | | lieu of an ASHRAE audit; |
| 4 | | (F) a description of the customer's plans to |
| 5 | | reallocate funds toward internal energy efficiency |
| 6 | | efforts identified in the subparagraph (E) report, |
| 7 | | including, but not limited to: (i) strategic energy |
| 8 | | management or other programs, including descriptions |
| 9 | | of targeted buildings, equipment and operations; (ii) |
| 10 | | eligible energy efficiency measures; and (iii) |
| 11 | | expected energy savings, itemized by technology. If |
| 12 | | the subparagraph (E) audit report identifies that the |
| 13 | | customer currently utilizes the best available energy |
| 14 | | efficient technology, equipment, programs, and |
| 15 | | operations, the customer may provide a statement that |
| 16 | | more efficient technology, equipment, programs, and |
| 17 | | operations are not reasonably available as a means of |
| 18 | | satisfying this subparagraph (F); and |
| 19 | | (G) a verification signed by a plant manager or an |
| 20 | | authorized corporate officer attesting to the |
| 21 | | truthfulness and accuracy of the information contained |
| 22 | | in the application. |
| 23 | | (3) Upon receipt of a properly and timely noticed |
| 24 | | request for opt out submitted by an eligible large private |
| 25 | | energy customer, the natural gas utility shall grant the |
| 26 | | request and file the request with the Commission, and, |
|
| | 10400SB0025ham005 | - 33 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | beginning January 1 of the first year of the next |
| 2 | | multi-year energy efficiency plan cycle, the opted out |
| 3 | | customer shall no longer be assessed the costs of the plan |
| 4 | | and shall be prohibited from participating in that |
| 5 | | multi-year plan cycle to give the natural gas utility the |
| 6 | | certainty to design program plan proposals. |
| 7 | | (4) The request to opt out is only valid for the |
| 8 | | requested plan cycle. An eligible large private energy |
| 9 | | customer must also request to opt out for future energy |
| 10 | | efficiency plan cycles, otherwise the customer will be |
| 11 | | included in the future energy efficiency plan cycle. |
| 12 | | (n) The applicability of this Section to customers |
| 13 | | described in subsection (m) of this Section is conditioned on |
| 14 | | the existence of the SDC program. In no event will any |
| 15 | | provision of this Section apply to such customers after |
| 16 | | January 1, 2020. |
| 17 | | (o) Utilities' 3-year energy efficiency plans approved by |
| 18 | | the Commission on or before the effective date of this |
| 19 | | amendatory Act of the 99th General Assembly for the period |
| 20 | | June 1, 2014 through May 31, 2017 shall continue to be in force |
| 21 | | and effect through December 31, 2017 so that the energy |
| 22 | | efficiency programs set forth in those plans continue to be |
| 23 | | offered during the period June 1, 2017 through December 31, |
| 24 | | 2017. Each utility is authorized to increase, on a pro rata |
| 25 | | basis, the energy savings goals and budgets approved in its |
| 26 | | plan to reflect the additional 7 months of the plan's |
|
| | 10400SB0025ham005 | - 34 - | LRB104 07069 AAS 29445 a |
|
|
| 1 | | operation. |
| 2 | | (Source: P.A. 103-613, eff. 7-1-24.)"; and |
| 3 | | on page 721, by replacing lines 1 through 4 with the following: |
| 4 | | "(1) has a nameplate generating capacity no greater |
| 5 | | than 5,000 kilowatts and is primarily used to offset a |
| 6 | | customer's electricity load, or as otherwise as defined |
| 7 | | for community renewable generation projects in Section |
| 8 | | 1-10 of the Illinois Power Agency Act;"; and |
| 9 | | on page 810, line 20, after "attributes", by inserting "to |
| 10 | | ensure customers are not double-billed for the same service"; |
| 11 | | and |
| 12 | | on page 846, by replacing lines 15 through 19 with the |
| 13 | | following: |
| 14 | | "made pursuant to subsection (b-10) of Section 16-111.5.". |