2847.1.
(a) (1) The commission shall, by December 31, 2018, determine the actual percentage of kilowatthours delivered by each load-serving entity during the peakload time period to end-use customers in the state that is derived from clean peak resources.(2) The commission shall ensure that each load-serving entity, in addition to the percentage determined pursuant to paragraph (1), procures a minimum percentage of kilowatthours delivered during the peakload time period from clean peak resources on at least 15 days every month in accordance with the following schedule:
(A) An additional 5 percent of electricity delivered during the peakload time period on the
required number of days each month in the year 2020 shall be supplied by clean peak resources.
(B) An additional 6 percent of electricity delivered during the peakload time period on the required number of days each month shall be supplied by clean peak resources every third year thereafter until December 31, 2029, or until 40 percent of demand during the peakload time period is supplied by clean peak resources, whichever occurs earlier.
(3) Contributions toward the standard set pursuant to paragraph (2) from an energy storage system shall be prorated based on the share of renewable energy resources used to charge the energy storage system.
(4) Clean peak resources shall use Independent System Operator-approved performance measurement solutions.
(5) The
commission shall ensure the clean peak resources provide benefits to the grid.
(6) The commission shall determine an appropriate mechanism for determining compliance with the clean peak standard, which may include the use of tradeable credits.
(7) The commission shall consider clean flexible capacity procurement targets to encourage deployment of clean peak resources to provide additional ancillary and ramping services.
(b) (1) Each local publicly owned electric utility shall, by December 31, 2018, determine the actual percentage of kilowatthours delivered during the peakload time period to its end-use customers that is derived from clean peak resources.
(2) Each local publicly owned electric utility, in addition to the percentage
determined pursuant to paragraph (1), shall procure a minimum percentage of kilowatthours delivered during the peakload time period from clean peak resources on at least 15 days every month in accordance with the following schedule:
(A) An additional 5 percent of electricity delivered during the peakload time period on the required number of days each month in the year 2020 shall be supplied by clean peak resources.
(B) An additional 6 percent of electricity delivered during the peakload time period on the required number of days each month shall be supplied by clean peak resources every third year thereafter until December 31, 2029, or until 40 percent of demand during the peakload time period is supplied by clean peak resources, whichever occurs earlier.
(3) Each local publicly owned electric utility shall ensure
the clean peak resources provide benefits to the grid.